History
2004
BMGS formed 2004
2007
ABIMS formed – Televiewer, gyro and downhole geophysical data collection
2016
IMS Formed – Mine Engineering management services
2018
BMGS/IMS were engaged by Hawthorn Resources to manage mining operations at Trouser Legs Project. Our team of experts brought valuable knowledge the efficient and safe operation of the mine, optimizing production and minimizing potential risks.
Location: Eastern Goldfields
Client: Hawthorn Resources
Commodity: Gold
Duration: 24 mths
Tonnes Mined: 552000
Ounces Rec: 43000
Cost Per Ounce: $1,400
2020
BMGS purchase first excavator
2020
BMGS/IMS Successfully complete mining operations at Blackjack Project
Location: Menzies
Client: Private
Commodity: Gold
Duration: 1 mth
Tonnes Mined: 25000
Ounces Rec: 1585
Cost Per Ounce: $1,380
2021
BML Ventures (BMLV) formed
2021
BMLV sign agreement with Resources and Energy Group (REZ) to mine/profit share Granny Venn project.
2022
BMLV sign agreement with Auric Mining to mine/profit share Jeffreys find deposit
2022
BMLV completes mining operations at Granny Venn
Location: Menzies
Client: Resources and Energy
Commodity: Gold
Duration: 10 mths
Tonnes Mined: 110000
Ounces Rec: 6442
Cost Per Ounce: $2,363
2022
BMLV sign agreement with Kingswest (now Brightstar) to mine/profit share Selkirk deposit
May – Sep 2023
Sep 2023 Jeffreys find stage 1 completed
Location: Norseman
Client: Auric Mining
Commodity: Gold
Duration: 12 mths
Tonnes Mined: 176000
Ounces Rec: 9741
Cost Per Ounce: $2,380
Sept 2023 – March 2024
BML completes mining Selkirk March 2024
Location: Menzies
Client: Brightstar ( Kingswest)
Commodity: Gold
Duration: 10 mths
Tonnes Mined: 43000
Ounces Rec: 7500
Cost Per Ounce: $1,550
August 2024
Second Mining fleet starts at Phillips find (Horizon Minerals)
April 2024 – July 2025
Jeffreys Find stage 2 mining/milling completed
Location: Norseman
Client: Auric Mining
Commodity: Gold
Duration: 15 mths
Tonnes Mined: 457400
Ounces Rec: 19750
Cost Per Ounce: $3393
December 2024 – August 2025
BMLV completes GAC mining project on time and below budget
Location: Wiluna
Client: Wiluna Mining Limited
Commodity: Gold
Duration: 8 mths
Tonnes Mined: 382000
Ounces Rec: 21937
Cost Per Ounce: $2,050
August 2024 – November 2025
BMLV completes Phillps Find mining project
Location: Coolgardie
Client: Horizon Minerals
Commodity: Gold
Duration: 16 months
Tonnes Mined: 276000 EST
Ounces Rec: 13500 EST
Cost Per Ounce: TBD









































